Sherwood Lane Water Repair

BE19-27

Completion Date: 
June 28, 2019

Contractor: Southeast Earthmovers

Contract Amount: $69,400


Project Manager: Paul Beck
Phone: 907-586-0882
Email: [email protected]
No Featured Image - Stock photo with plans and pencils and the words No Featured Image.

Description:

The WORK covered in the Contract Documents includes replacement of the ductile iron water main crossing within an existing 20” steel casing under Glacier Highway adjacent to Sherwood Lane, traffic control, replacement of an existing 12” gate valve, sheeting, shoring and bracing, trenching, excavation and backfill, removal and replacement of impacted asphalt bike path and other miscellaneous related WORK.